Name |
Roles |
Email Address |
|
Project Manager, Requirements |
|
Tim Jasko |
Design, Implementation |
|
Chris Scribner |
Design, Implementation |
|
Steve Hoelle |
Design, Implementation |
|
Court Caldwell |
Testing, Requirements |
|
Matt Stupca |
Testing, Requirements |
|
Alex Kutsenok |
Configuration Manager |
Work Package ID |
Resource Names |
Role |
Task |
Start |
Finish |
% Work Completed |
1 |
Zach |
Project Manager |
2nd Quarter Project Plan |
|
|
100% |
2 |
Matt Court |
Testing Team |
Validation Test Plan |
|
|
100% |
3 |
Chris Tim Steve |
Design Team |
Design Document |
|
|
100% |
4 |
Matt Court |
Testing Team |
Integration Test Plan |
|
|
100% |
5 |
Tim Steve Chris |
Implementation Team |
Final Project Implementation |
|
05/11/2003 |
90% |
6 |
Alex |
Configuration Manager |
Project Presentation #2 |
|
|
100% |
7 |
Alex |
Configuration Manager |
Complete Project Webpage |
? |
|
100% |
8 |
Court |
|
Math Notation Solution (Ruled Infeasible) |
|
|
0% |
9 |
Chris Tim Steve |
Design Team |
Document on Infeasibility of Math Notation |
|
|
100% |
10 |
Chris Tim Steve |
Design Team |
Math Notation Workaround |
|
|
100% |
Week Starting |
On/Off Schedule |
Reason Off Schedule |
Corrective Actions To Take |
|
ON |
N/A |
N/A |
|
ON |
N/A |
N/A |
|
OFF |
Integration Test Plan Not Complete |
Get it finished by next week. |
|
OFF |
Integration Test Plan Still Not Complete |
It must be finished by next week. |
|
OFF |
Integration Test Plan / Implementation |
Implementation ran into issues, which made integration testing impossible. Will be resolved by next week. |
|
ON |
N/A |
N/A |
Items |
None |
Date |
Name |
Revision |
|
Zach |
Finally completed 2nd Quarter Project Plan. |
|
Zach |
Performed Schedule Update |
|
Zach |
Performed Schedule Update, Added Work Package #9 |
|
Zach |
Performed Schedule Update, Added Work Package #10 |
|
Zach |
Performed Schedule Update |
|
Zach |
Completed Document |