Project Plan (2nd Quarter)

Calculus Review Site

Zach Lute


 

Table of Contents

·       Personnel

·       Work Packages

·       Project Schedule Update

·       To Do List

·       Revision History


Personnel

Name

Roles

Email Address

 Zach Lute

Project Manager, Requirements

lutezp@rose-hulman.edu

 Tim Jasko

Design, Implementation

jaskotp@rose-hulman.edu

 Chris Scribner

Design, Implementation

scribnc@rose-hulman.edu

 Steve Hoelle

Design, Implementation

hoellesd@rose-hulman.edu

 Court Caldwell

Testing, Requirements

caldwecr@rose-hulman.edu

 Matt Stupca

Testing, Requirements

stupcamc@rose-hulman.edu

 Alex Kutsenok

Configuration Manager

kutsenav@rose-hulman.edu


Work Packages

Work Package ID

Resource Names

Role

Task

Start

Finish

% Work Completed

1

Zach

Project Manager

 2nd Quarter Project Plan

03/30/2003

04/07/2003

100%

2

Matt

Court

Testing Team

 Validation Test Plan

01/23/2003

03/30/2003

100%

3

Chris

Tim

Steve

Design Team

 Design Document

02/20/2003

04/07/2003

100%

4

Matt

Court

Testing

Team

 Integration Test Plan

03/30/2003

04/27/2003

100%

5

Tim

Steve

Chris

Implementation Team

 Final Project Implementation

03/30/2003

05/11/2003

90%

6

Alex

Configuration Manager

 Project Presentation #2

05/05/2003

05/12/2003

100%

7

Alex

Configuration

Manager

 Complete Project Webpage

?

05/12/2003

100%

8

Court

 

 Math Notation Solution (Ruled Infeasible)

03/30/2003

04/14/2003

0%

9

Chris

Tim

Steve

Design Team

  Document on Infeasibility of Math Notation

04/28/2003

05/05/2003

100%

10

Chris

Tim

Steve

Design Team

  Math Notation Workaround

05/04/2003

05/11/2003

100%

Project Schedule Update

  • Week Starting - Monday's date for the week
  • On/Off Schedule - Put in On if on schedule and Off if not on schedule
  • Reason Off Schedule - brief, but specific description of why the project is off schedule
  • Corrective Actions To Take - brief, but specific description of what will be done to get the project back on schedule>

Week Starting

On/Off Schedule

Reason Off Schedule

Corrective Actions To Take

04/07/2003

ON

  N/A

  N/A

04/14/2003

ON

  N/A

  N/A

04/27/2003

OFF

  Integration Test Plan Not Complete

  Get it finished by next week.

05/04/2003

OFF

  Integration Test Plan Still Not Complete

  It must be finished by next week.

05/11/2003

OFF

  Integration Test Plan / Implementation

  Implementation ran into issues, which made integration testing   

  impossible.  Will be resolved by next week.

5/18/2003

ON

  N/A

  N/A


To Do List

Items

None 


Revision History

Date

Name

Revision

04/07/2003 

Zach

Finally completed 2nd Quarter Project Plan.

04/14/2003

Zach

Performed Schedule Update

04/27/2003

Zach

Performed Schedule Update, Added Work Package #9

05/04/2003

Zach

Performed Schedule Update, Added Work Package #10

05/11/2003

Zach

Performed Schedule Update

05/18/2003

Zach

Completed Document